API 650 New Tank Construction Welding Inspection
Technical Reference: This page is a clause-level inspection reference for API 650 new tank construction — covering inspection hold points by construction phase, NDT requirements by weld joint category, common nonconformance examples, and the documentation turnover package. For our full range of tank capabilities including API 653 in-service inspection and AWWA D100 water tank inspection, see our Tank Welding Inspection Service page.
API 650 — Welded Tanks for Oil Storage — governs the design, materials, fabrication, erection, and testing of new aboveground welded steel storage tanks. Unlike API 653 (which addresses existing tanks), API 650 applies exclusively during new construction. Every welded joint on a new API 650 tank is subject to inspection requirements that vary by weld location, joint category, tank size, and service conditions. AWSCWI.COM provides AWS CWI certified inspectors with hands-on API 650 field erection experience for new tank construction projects nationwide.
API 650 Scope and Annex Applicability
API 650 covers carbon steel and stainless steel tanks storing petroleum products, chemicals, and other liquids at pressures approximating atmospheric. The standard uses a modular annex structure — the main body covers standard carbon steel tanks for non-refrigerated service, while annexes activate based on design conditions, materials, or owner specifications. The inspector must confirm at the pre-construction meeting which annexes are invoked. Failure to identify applicable annexes before construction begins causes missed inspection hold points and scope gaps that are difficult to recover downstream.
Annex E — Seismic Design
Required for tanks in seismic regions. Governs anchorage, freeboard, and sloshing loads. Triggers additional inspection of anchor bolt chairs and base plate welds.
Annex F — Internal Pressure
Applies to tanks operating above atmospheric but below 2.5 psig. Additional weld joint inspection requirements for frangible and non-frangible roof-to-shell connections.
Annex M — Frangible Roof Joint
Critical hold point: the roof-to-shell junction must fail before the shell-to-bottom joint under internal overpressure. Weld sizing is an inspector verification point — overwelding defeats the safety function.
Annex S / SC — Stainless Steel
Austenitic (Annex S): inspection for sensitization and chloride contamination. Duplex (Annex SC): ferrite content verification and interpass temperature monitoring required.
Inspection Hold Points by Construction Phase
API 650 new tank construction follows a defined sequence — foundation, bottom, shell erection, roof, and appurtenances. Each phase has specific inspection hold points that must be cleared before the next phase proceeds. Missing a hold point means the weld becomes inaccessible or the condition becomes unverifiable after subsequent work covers it.
1 Foundation and Ringwall Verification
Before any steel arrives, the inspector verifies foundation readiness per API 650 Section 7:
- Ringwall elevation survey — Verify levelness per API 650 Table 7-2 tolerances. For tanks over 120 ft diameter, maximum deviation between any two points on the ringwall is ½ inch. An out-of-level foundation creates fit-up problems in every subsequent phase.
- Anchor bolt placement — If Annex E seismic design applies, verify bolt location, projection, and template alignment per the certified seismic design drawing. Anchor bolt chair welds on the shell are a later inspection point.
- Foundation surface condition — Confirm the bearing surface is clean, level, and prepared per the project specification (sand pad, oiled sand, grout, or concrete).
2 Bottom Plate Layout, Fit-Up, and Welding
Tank bottom construction is the most inspection-intensive phase per linear foot of weld. Bottom plates, sketch plates, and the annular ring all require verification before, during, and after welding.
- Material verification (MTRs) — Confirm annular ring plate material meets the specification. API 650 Table 5-1a requires annular ring material at least equal to the first shell course material grade. This is a common NCR point — annular plates arriving with incorrect material grade because procurement confused bottom plate and annular ring requirements.
- Annular ring fit-up — Radial width must meet minimums per API 650 Table 5-1a based on first shell course thickness and product stress. Measured from the inside edge of the shell plate to the annular plate edge — not from the weld toe.
- Bottom plate lap weld inspection — Fillet welds per Section 5.1.5. Verify continuous weld (no skip welding), adequate throat, and acceptable profile.
- Three-plate junction inspection — Per Section 5.1.5.5. The three-plate lap creates a stress riser. Minimum spacing between junctions and between junctions and the annular ring butt weld are code requirements the inspector must verify during layout — before welding starts.
- Annular ring butt welds — Full-penetration butt welds. Highest-criticality welds on the tank bottom. RT or UT required per Section 8 based on annular thickness.
- Vacuum box testing — Section 8.6 requires vacuum box testing of all bottom plate seam welds and the bottom-side fillet weld of the shell-to-bottom joint. Mandatory hold point — must be completed and accepted before the tank is filled.
3 Shell Erection and Welding
Shell courses are erected either by conventional method (bottom course first, stacking upward) or jacking method (top course first, jacking upward). Inspection approach differs by erection method, but weld acceptance criteria are the same.
- Shell plate layout verification — Verify plate arrangement matches the certified shell layout drawing. Vertical weld seam stagger between courses must meet the minimum offset per Section 5.2 (minimum 5t or 6 inches, whichever is greater).
- Vertical shell seam inspection — Butt welds with full penetration. Verify joint fit-up, root gap, and backing strip (if used) before welding. Peaking at vertical weld joints must not exceed Section 7.5 tolerances.
- Horizontal shell seam inspection — Banding (inward or outward bulge) must not exceed Section 7.5 tolerances. Checked using a horizontal sweep board or template.
- Shell-to-bottom weld — Fillet weld (inside and outside) connecting the lowest shell course to the annular ring. Most structurally critical fillet weld on the tank. Section 5.1.5.7 specifies minimum fillet sizes based on shell course thickness. Both sides require VT; bottom side must pass vacuum box testing.
- Shell roundness and plumbness — Section 7.5 tolerances for shell radius at each course and overall plumbness. Measurements taken at each course as erection progresses — not just at completion.
- Nozzle and manway welds — Reinforcement per Section 5.7. Verify reinforcement pad size, pad-to-shell weld, nozzle neck-to-shell weld (full penetration through shell plate), and telltale hole (weep hole). The telltale hole must remain open — it serves as a leak indicator for the pad-to-shell seal weld.
4 Roof Construction
- Supported cone roof — Rafter-to-girder welds, column base plate welds, and rafter-to-shell clip connections. Roof plate lap welds are fillet welds similar to bottom plate construction.
- Self-supporting cone or dome roof — Roof plate butt welds or lap welds per design. Compression ring at the roof-to-shell junction is a critical inspection point.
- Frangible roof joint (Annex M) — The roof-to-shell weld must be sized to fail before the shell-to-bottom joint under overpressure. Verify fillet size does not exceed the maximum specified in the design. Overwelding defeats the safety function — this is a hold point, not a documentation item.
- Floating roof — Pontoon compartment seal welds, deck plate welds, rim-to-pontoon welds. Each pontoon compartment individually pressure tested for leak tightness.
5 Appurtenances, Testing, and Closeout
- Wind girder and stiffening ring welds — Intermediate and top wind girder attachment welds. Verify continuous attachment per design and adequate fillet size.
- External piping attachment welds — Pipe support clips, stairway/platform brackets. Often made by non-tank trades (piping or structural crews) who may not be covered by the tank welding procedures. The inspector must verify WPS qualification covers these welds.
- Hydrostatic test — Section 8.5 requires filling to the design liquid level with water. Monitor for leakage at all welded joints, check shell settlement during filling per Table 8-1, and document observations. Foundation settlement readings taken at prescribed fill intervals.
- Pneumatic test of roof (if applicable) — Roof-to-shell welds may be tested by applying internal air pressure per Section 8.5 limitations. Maximum test pressure must not be exceeded — over-pressuring can damage the frangible joint.
NDT Requirements by Weld Joint Category
API 650 Section 8 prescribes NDT requirements based on weld joint location and tank design. The extent of examination varies — some joints require 100% volumetric examination, others require spot examination, and some require only visual inspection. Annex requirements and purchaser supplemental specifications may increase these code minimums.
| Weld Joint Location | Joint Type | NDT Method | Extent of Examination | Clause Ref. |
|---|---|---|---|---|
| Vertical shell seams — all courses | Butt (CJP) | RT or UT | Spot (per 8.1.2) — or 100% for tanks exceeding design stress thresholds | 8.1.1, 8.1.2 |
| Horizontal shell seams | Butt (CJP) | RT or UT | Spot — typically 1 per 100 ft of horizontal seam or per purchaser spec | 8.1.1, 8.1.2 |
| Shell-to-bottom fillet weld | Fillet | VT + Vacuum Box (bottom side) | 100% visual, 100% vacuum box on bottom side | 8.6 |
| Annular ring butt welds | Butt (CJP) | RT or UT | Per Section 8 based on annular thickness — 100% at or above threshold | 8.1.1 |
| Bottom plate lap welds | Fillet (lap) | VT + Vacuum Box | 100% visual, 100% vacuum box | 8.6 |
| Nozzle neck-to-shell welds | CJP through shell | VT; RT/UT if specified by purchaser | 100% VT; volumetric per purchaser spec | 5.7, 8.1 |
| Reinforcement pad-to-shell fillet welds | Fillet | VT + Pneumatic (via telltale hole) | 100% VT; soap bubble test through telltale hole | 5.7 |
| Roof plate welds (supported cone roof) | Fillet (lap) | VT | 100% visual | 5.10 |
| Roof-to-shell junction (frangible joint) | Fillet | VT — verify weld size does NOT exceed max | 100% VT; dimensional verification of fillet size | Annex M, 5.10 |
| Floating roof pontoon seal welds | Fillet | VT + Pneumatic (per compartment) | 100% VT; individual compartment pressure test | Annex H |
Key Inspector Takeaway: API 650 establishes minimum NDT requirements. Many purchasers — especially refinery and petrochemical operators — specify supplemental NDT beyond these minimums in their purchase order. The inspector must have both API 650 and the project-specific inspection plan before determining the actual NDT scope. Quoting API 650 minimums to justify skipping NDT that the purchaser specified is a documentation and contract failure, not an acceptable engineering judgment call.
Common Nonconformance Reports on New Tank Construction
Based on field experience across refinery, terminal, and industrial tank projects, these are the nonconformance conditions most frequently documented during API 650 new tank construction. Recognizing these patterns during planning and early construction phases prevents costly rework and schedule delays.
Material and Documentation NCRs
Annular Ring Material Mismatch
Annular plates arrive as A36 or A283 when the design requires A516-70 or equivalent per Table 5-1a. This happens when procurement treats annular plates as “bottom plates” on the purchase order. Caught during material receiving by comparing MTRs against the material specification on the certified tank drawing.
Missing or Incomplete MTRs
Plate material arrives without mill test reports, or MTRs do not include all required test values (chemical analysis, mechanical properties, heat treatment condition). Section 4 requires MTRs per ASTM A6/A6M for plates.
WPS Not Qualified for Position
Tank contractors qualify WPS for flat and horizontal positions but attempt vertical welding on shell courses without a position-qualified procedure. ASME Section IX governs WPS qualification for API 650 work.
Welder Qualification Gaps
Welder continuity lapsed, or a welder qualified on SMAW attempts FCAW without requalification. The inspector maintains a welder log tracking active qualifications against actual production welding.
Fabrication and Fit-Up NCRs
Vertical Seam Misalignment (High-Low)
Shell plate edges offset beyond the tolerance in Section 7.3. Common on thicker courses where plate rolling imperfections create edge mismatch. Must be corrected before welding or addressed with an engineering disposition.
Excessive Root Gap
Root opening exceeds the WPS-qualified range. Field crews sometimes spread the gap to compensate for short plates or thermal contraction. Requires engineering review for buildup procedures or plate replacement.
Three-Plate Junction Spacing
Bottom plate layout positions three-plate junctions closer than minimum spacing to each other or to annular ring butt welds. Must be caught during layout — before welding — because reworking after welding is extremely costly.
Peaking and Banding Out of Tolerance
Vertical weld peaking and horizontal seam banding exceed Section 7.5 limits. Develop during welding; measured after completion. Correction requires controlled heat application or mechanical straightening per an approved procedure.
Frangible Joint Overwelding
Roof-to-shell frangible joint weld exceeds the maximum size. Safety-critical NCR: the joint must separate under overpressure before the shell-to-bottom joint fails. Correctable by grinding, but requires engineering approval and re-inspection.
NDT and Testing NCRs
Vacuum Box Testing Failures
Bottom seam welds or shell-to-bottom fillet welds leak during vacuum box testing. Persistent failures often indicate a welding procedure or welder technique issue requiring root cause investigation — not just repeated repair and retest.
RT/UT Rejection of Shell Seams
Volumetric examination reveals incomplete fusion, porosity, slag, or lack of penetration. Section 8.4 repair, re-examination, and expanded examination requirements apply. Two or more rejected spot shots on the same increment trigger 100% examination.
Hydrostatic Test Settlement
Foundation settlement during hydrotest exceeds Table 8-1 allowables. Settlement exceeding uniform or differential limits requires engineering evaluation before the tank is accepted for service.
Purchaser vs. Code-Required Inspection
A critical distinction on any API 650 project is the difference between what the code requires as minimum inspection and what the purchaser specifies in supplemental requirements. The inspector must work from both documents.
Code-Required Minimums (Section 8)
API 650 Section 8 establishes mandatory inspection and testing requirements that apply to all new tank construction regardless of the purchaser’s specification: visual examination of all welds, spot radiographic or ultrasonic examination of shell butt welds, vacuum box testing of bottom and shell-to-bottom welds, and hydrostatic testing. These are non-negotiable — the tank cannot be accepted without meeting Section 8 requirements.
Common Purchaser Supplemental Requirements
Most petroleum and chemical operators add inspection requirements beyond API 650 minimums:
- • 100% RT or UT of all shell butt welds (versus spot examination for standard tanks)
- • MT or PT of shell-to-bottom fillet welds in addition to vacuum box testing
- • PMI verification of all pressure-boundary materials
- • Tighter NDE acceptance criteria (e.g., ASME Section VIII standards applied to tank shell welds)
- • Additional witness/hold points beyond Section 8 requirements
- • PWHT requirements based on thickness or service conditions not triggered by the code alone
- • Owner-specific documentation formats, photo protocols, and NCR tracking systems
Per Section 1.1.2, the purchaser may specify requirements more stringent than the standard. The inspector cannot waive purchaser requirements by citing the code — the purchase order governs.
Shop Fabrication vs. Field Erection Inspection
Most API 650 tanks are field-erected, but significant fabrication work occurs in the shop. The inspector’s scope may include shop surveillance, field erection inspection, or both depending on the contract.
Shop Fabrication Scope
Plate cutting, rolling, beveling, and shop welding of nozzle assemblies, manways, reinforcement pads, roof structural members, stairway/platform components, and wind girder sections. Focus: material verification (MTRs vs. plate markings), dimensional verification of rolled shell plates, WPS and welder qualification review, and weld quality on pre-fabricated assemblies.
Field Erection Scope
Where the majority of inspection hours are spent. Covers all construction phases plus ongoing verification of welding consumables (electrode storage, baking/holding temperatures for low-hydrogen electrodes), environmental conditions (preheat, interpass temperature, wind protection), and welder identification/traceability.
Final Documentation and Turnover Package
API 650 Section 10 requires a Manufacturer’s Data Report upon completion. The complete documentation turnover package for a new API 650 tank becomes the baseline record for all future API 653 in-service inspections. A complete, well-organized package with traceable weld maps and material records significantly reduces the cost and complexity of the tank’s first in-service inspection. When original construction documentation is incomplete or missing, the in-service inspector must make conservative assumptions that often result in more extensive inspection and earlier repair requirements.
Documentation Turnover Checklist
- Manufacturer’s Data Report — Per Section 10. Signed by manufacturer and inspector. Certifies construction per API 650 and the purchase order.
- Certified tank drawings (as-built) — Shell layout, nozzle orientation, foundation plan. Field deviations documented on as-built drawing.
- Material test reports (MTRs) — All pressure-boundary materials: shell, annular ring, bottom plates, nozzle necks, flanges, reinforcement pads, roof plates. Traceable to installed plate locations.
- Welding Procedure Specifications and PQRs — All WPS used during construction with supporting Procedure Qualification Records per ASME Section IX.
- Welder qualification records — Performance Qualification Records for all welders with continuity documentation.
- Weld map (roll-out) — All weld joints, welder identification per joint, NDT status. Critical for future API 653 inspection.
- NDT reports — All RT, UT, MT, PT, and VT examination reports with acceptance/rejection disposition. Includes repair and re-examination records.
- Vacuum box test records — Coverage maps and results for all bottom and shell-to-bottom welds.
- Hydrostatic test records — Fill rate logs, settlement readings at prescribed intervals, leak observations, final acceptance.
- Nonconformance reports — All NCRs with dispositions (repair, accept-as-is with engineering justification, or reject/replace).
- Calibration records — NDT equipment, welding machines (amperage/voltage verification), measuring instruments.
- Foundation settlement survey — Pre-hydrotest and post-hydrotest settlement readings per Table 8-1.
Professional final documentation turnover services ensure systematic verification and organization of all inspection records before operational handover — preventing gaps that complicate future inspections or regulatory audits.
AWSCWI.COM API 650 Inspection Capabilities
AWSCWI.COM provides AWS CWI certified inspectors with direct field experience on API 650 new tank construction projects for petroleum storage, chemical storage, water storage (AWWA D100), and industrial applications. Our tank inspectors hold API 653 certification in addition to AWS CWI, providing continuity between new construction requirements and future in-service inspection needs.
API 650 Inspection Service Scope
- • Pre-construction document review — WPS, PQR, welder qualifications, ITP, and project specifications
- • Shop fabrication surveillance — Material verification, dimensional checks, pre-fabricated assembly inspection
- • Field erection inspection — All construction phases from foundation through hydrostatic test
- • NDT coordination — RT, UT, MT, PT, VT, vacuum box testing
- • Hydrostatic test witnessing — Fill monitoring, settlement measurement, leak observation
- • NCR documentation and tracking — Nonconformance identification, disposition coordination, repair verification
- • Documentation package assembly — Turnover verification per Section 10 and purchaser requirements
We deploy to tank construction projects nationwide with typical mobilization within 48–72 hours depending on location and inspector availability. For multi-tank construction programs or extended duration projects, we provide dedicated inspectors for the full project duration. Day rates start at $1,280 for AWS CWI tank inspection services.
Schedule API 650 New Tank Construction Inspection
AWSCWI.COM — AWS CWI certified tank inspectors with API 650 field erection experience. Nationwide deployment. COI provided.
(855) 729-3111
Tank Welding Inspection Services Inspector CertificationsThis technical reference is maintained by AWSCWI.COM as a clause-level resource for API 650 new tank construction welding inspection. For API 653 in-service inspection, tank repair inspection, or AWWA D100 water tank inspection, visit our Tank Welding Inspection Service hub page.